Prioritisation of bugs
We need an agreed definition or understanding on the priority of the bugs we find during testing. The following is my suggested approach, but I am open to feedback
Rating | Action | Urgency |
---|---|---|
Highest | Must be fixed | Within 24 hours (if at all possible), as it delays other testing |
High | Must be fixed | Within one week (if at all possible), but before go-live |
Medium | Must be fixed | Should be fixed before go live, but can be later so long as fixed in the project. Could allow for fixing in the next phase of the project. |
Low | Should be fixed | Should be fixed in the project, but can be left for BAU to address later |