Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 4 Next »

Draft

PhaseDates(?)Notes
1 - Discovery

End Sprint 14 - early July 2015

(Sprint 15 contingency)

CSP, F&S's

  • Approved approach for CSP - CSP vs F&S (PMO)
  • Straw-person for F&S (PMO, Faculty Managers group)
  • Subject and programme template (PMO, CSP Ref group)
  • Subjects and clustering (PMO, CSP Ref group)
  • Initial round of testing planned (team)

Other

  • Agreed high level approach for PG, and sites in scope
  • Agreed high level approach for Research Centres, and sites in scope
  • Agreed high level approach for Student Information, and sites in scope
  • Agreed approach for web governance - I don't think this is achievable as will require wider consultation
2 - CSP, F&STBC

Early

  • Priorities/order of faculties
  • Monthly meeting across all faculties scheduled
  • Course requirements to be reviewed from COO
3 - PostgraduateTBC

 

4 - Research CentresTBC

 

5 - Student InformationTBC

 

  • No labels