Introduce (at least) F&S stakeholders (i.e. those most impacted, probably content owners/editors) to WIP IIObtain approval for all HLS documents: Via PMO to give certainty Additional analysis can happen before or after.9
 Obtain approval for the horizontal and vertical scope 
 Finalise presentation for key stakeholders: Need a version for PMO, senior stakeholders and content owners9
 Prepare high level project plan: Showing at least the F&@S coverage over time, probably with key resources blocked in. At this level is it a roadmap rather than a project plan?9/10
 Draft content strategies for all HLS and/or global menu areas9/10
 Validate user needs: At least those where the business requirements for WIP II assume specific user needs. Could also create an epic for user research and have one task in this phase.10
 Brief all senior stakeholders in F&S: MS to prepare the ground so team can meet with content owners.10
 Brief stakeholders/content owners in F&S: Introduce our stakeholders to the project (problem, approach, timing, benefits, solution options, etc).11
Complete processes/artefacts required to close the initiation/establishment phaseDraft a project purpose statement and an elevator pitch9
 Draft success measures and targets9
 Establish a RIDS register9
 Establish the required project management methodologies (e.g. change, risk/issue, governance, reporting,release, etc.).10
  Establish the required reference groups10
  Establish the priorities/order of scope, budget, time and quality 
   
 Document all know business requirements in epic-story/task forma9
 Document all know user requirements in epic-story/task forma10
   

...