Draft

 TBC
PhaseDates(?)Key DeliverablesNotesDependenciesConsultation
1 - Discovery

End Sprint 14 - early July 2015

(Sprint 15 contingency)

 

CSP, F&S's

  • Approved approach for CSP - CSP vs F&S (PMO)
  • Straw-person for F&S (PMO, Faculty Managers group)
  • Subject and programme template (PMO, CSP Ref group)
  • Subjects and clustering (PMO, CSP Ref group, F&S's)
  • Initial round of testing planned (team)

Other

  • Agreed high level approach for PG, and sites in scope
  • Agreed high level approach for Research Centres, and sites in scope
  • Agreed high level approach for Student Information, and sites in scope
  • Agreed approach for web governance - I don't think this is achievable as will require wider consultation
  
2 - CSP, F&STBC

Topics/subjects taxonomy - 1 or 2 releases planned

Topic and programme pages - delivery approach tbc (but topics and associated programmes planned for dual release as a minimum)

Staff profiles - new approach which are likely centralised and referenced within faculty and school sites as appropriate (people finder tool)

Events - likely to be a deliverable of functionality within F&S and other 'sites'

Faculty and school pages - multiple changes across the channel:

Build new sites for:

  • faculty sites
  • school sites

Move content into:

  • current students
  • engagement hub?
  • victoria abroad
  • research
  • library?
  • about

Early

  • Priorities/order of faculties
  • Monthly meeting across all faculties scheduled
  • Course requirements to be reviewed from COO
  
3 - PostgraduateTBC 

 

  
4 - Research CentresTBC

 

 5 - Student Information