PhaseDates(?)Notes
1 - Discovery

End Sprint 14 - early July 2015

(Sprint 15 contingency)

  • Approved approach for CSP
  • Straw-person for F&S
  • Agreed high level approach for PG, and sites in scope
  • Agreed high level approach for Research Centres, and sites in scope
  • Agreed high level approach for Student Information, and sites in scope
  • Agreed approach for web governance
2 - CSP, F&STBC

 Early

  • Priorities/order of faculties
  • Monthly meeting across all faculties scheduled
3 - PostgraduateTBC

 

4 - Research CentresTBC

 

5 - Student InformationTBC